Riverland Community College is first college to achieve energy efficiency upgrades with Minnesota GESP help
Riverland Community College, with campuses in Albert Lea, Austin, and Owatonna, used an Energy Savings Performance Contract (ESPC) to make major energy upgrades throughout its facilities. It was the first college to use the state’s Guaranteed Energy Savings Program (GESP) to oversee its project, which focused on improving lighting, lighting controls, energy management controls, building envelope, chiller controls, and water conservation measures such as faucet aerator retrofits. The project was completed in fall 2017 and is expected to reduce energy use
by 27% and yield cost savings of $136,632 per year. The project is being paid for over 15 years via energy, operation and maintenance savings, which are guaranteed by Honeywell, the energy services company.
Aims & Objectives: The college looked at energy savings as a great way to implement building upgrades. “Retrofitting the lighting to LEDs and upgrading the building energy management system were the projects that motivated the college to pursue the Guaranteed Energy Savings Program,” said Brad Doss, Riverland's Chief Financial Officer. “However, completing the work through GESP enabled the college to also upgrade the building envelope and install water conservation measures as well.”
| Energy retrofit: Upgrades to building controls, building envelope, chiller controls, lighting controls, and replacement of campuswide lighting with LEDs. |
| Cost: $1.54 million |
| Annual energy savings: 7,733 MMBtu |
| Annual cost savings: $136,632 |
| Energy services company: Honeywell |
| State assistance: Guaranteed Energy Savings Program |
| Utility rebates: $81,525 |
| Project completed: Fall 2017 |
What’s more, the college was pleased that it could get all the work done “now,” Doss added. “The Guaranteed Energy Savings Program allowed Riverland Community College to get work done that the college would not have been able to do within our normal operating budget.”
Assessment & Energy Savings Performance Contract: Following a preliminary assessment of energy needs and opportunities, Honeywell performed a detailed analysis of the potential savings and costs for each accepted energy and water savings measure. The contractor prepared an Energy Savings Performance Contract
proposal to design, install, and monitor the energy and water saving measures proposed in the Investment Grade Audit Report.
Terms included:
- Project price;
- Complete list of services to be provided as related to each cost;
- Term of the contract;
- Description of financing options and recommendations;
- Explanation of how the savings will be calculated and adjusted; and
- Analysis of annual cash flow for the state institution during the contract term.
Implementation: The work was completed campus-wide in four buildings. Controls and lighting were retrofitted to meet campus needs. The control work focused on ensuring correct set points; recommissioning the heating, ventilation, and cooling system; proper programming; installing additional sensors; and upgrading the digital direct controls. Interior and exterior lights were retrofitted to LEDs. The West Campus chiller was retrofitted with controls and variable frequency drives to optimize the fan power. Austin West retrofitted their faucet aerators and upgraded to flushometers to save water. Last, building envelope upgrades were completed college-wide and included insulation, caulking, and installation of door sweeps to reduce air leakages.
Results/Benefits: In 2018, Riverland will document utility savings achieved in 2017 from its energy conservation measures. “If the college would have completed all of this work through a piecemeal approach, it would have taken years longer to get all the work done,” said Doss. In addition, Riverland was able to complete a couple of special projects through GESP, added Doss. “A side benefit of GESP was the ability to upgrade the theater lighting. The college doesn’t want staff to access the theater lighting often for safety reasons. Even though the theater lighting had a more than 120-year payback, the college was able to retrofit it with lower maintenance lighting and finance it through GESP, because the lower payback energy conservations measures helped pay for it.”
The college was excited by the energy savings achieved through the performance contract, and it was impressed by the additional building functionality achieved through the project. Shawn O’Connor, Riverland Community College Physical Plant Director, said “the updated building energy management system installed
allows Riverland to shut down additional parts of the college when not in use, which it has never been able to do before.”
What’s more, the energy services contract struck by Riverland and Honeywell included collaboration with a third party, the Guaranteed Energy Services Program, which provided support to the college every step of the way. GESP provided transparency to the process by evaluating the technical and financial feasibility of the Energy Services Company proposals and by providing project technical assistance to ensure that the cash flow and ESPC Measurement and Verification Plan were properly designed to ensure contract performance. “When challenges came up in the project, it was helpful to have technical assistance from the Department of Commerce available through GESP,” said O’Connor.
Archive
- March 2026 (2)
- February 2026 (3)
- January 2026 (1)
- December 2025 (1)
- November 2025 (2)
- October 2025 (2)
- September 2025 (4)
- June 2025 (2)
- May 2025 (2)
- April 2025 (7)
- February 2025 (2)
- January 2025 (2)
- December 2024 (2)
- October 2024 (2)
- September 2024 (2)
- August 2024 (2)
- June 2024 (3)
- May 2024 (1)
- April 2024 (5)
- March 2024 (6)
- February 2024 (1)
- January 2024 (3)
- December 2023 (3)
- November 2023 (1)
- October 2023 (4)
- September 2023 (2)
- August 2023 (3)
- June 2023 (2)
- May 2023 (1)
- April 2023 (2)
- February 2023 (4)
- January 2023 (1)
- October 2022 (2)
- September 2022 (1)
- August 2022 (3)
- July 2022 (1)
- April 2022 (1)
- March 2022 (3)
- January 2022 (1)
- December 2021 (1)
- November 2021 (1)
- October 2021 (2)
- September 2021 (4)
- June 2021 (3)
- May 2021 (4)
- April 2021 (5)
- March 2021 (1)
- February 2021 (2)
- November 2020 (3)
- October 2020 (1)
- September 2020 (2)
- July 2020 (3)
- June 2020 (1)
- May 2020 (5)
- February 2020 (3)
- January 2020 (2)
- December 2019 (1)
- September 2019 (4)
- August 2019 (3)
- July 2019 (1)
- June 2019 (1)
- April 2019 (4)
- March 2019 (4)
- February 2019 (4)
- January 2019 (1)
- November 2018 (2)
- September 2018 (2)
- July 2018 (1)
- June 2018 (1)
- April 2018 (3)
- February 2018 (5)
- November 2017 (2)
- October 2017 (1)
- September 2017 (2)
- August 2017 (4)
- June 2017 (1)
- April 2017 (3)
- February 2017 (2)
- January 2017 (3)
- December 2016 (1)
- November 2016 (3)
- October 2016 (2)
- September 2016 (2)
- August 2016 (5)
- June 2016 (1)
- May 2016 (2)
- April 2016 (4)
- February 2016 (2)
- January 2016 (6)
- December 2015 (6)
- November 2015 (6)
- October 2015 (2)
- September 2015 (8)
- August 2015 (2)
- July 2015 (2)
- June 2015 (1)
- May 2015 (3)
- April 2015 (1)
- March 2015 (4)
- February 2015 (8)
- January 2015 (1)
- December 2014 (1)
- November 2014 (1)
- October 2014 (4)
- September 2014 (3)
- August 2014 (1)
- July 2014 (5)
- June 2014 (6)
- May 2014 (3)
- April 2014 (1)
- March 2014 (2)
- February 2014 (4)
- December 2013 (2)
- November 2013 (2)
- October 2013 (6)
- September 2013 (1)
- August 2013 (5)
- July 2013 (4)
- June 2013 (5)
- May 2013 (5)
- April 2013 (10)
- March 2013 (6)
- February 2013 (6)
- January 2013 (2)
- December 2012 (2)
- November 2012 (2)
- October 2012 (2)
- September 2012 (2)
- August 2012 (5)
- July 2012 (4)
- June 2012 (4)
- May 2012 (3)
- April 2012 (5)
- March 2012 (2)
- February 2012 (3)
- January 2012 (4)
- December 2011 (2)
- November 2011 (5)
- October 2011 (10)
- September 2011 (3)
- August 2011 (4)
- July 2011 (5)
- June 2011 (2)
- May 2011 (3)
- April 2011 (11)
- March 2011 (1)
- February 2011 (3)
- January 2011 (3)
- December 2010 (2)
- November 2010 (2)
- October 2010 (2)
- September 2010 (2)
- August 2010 (2)
- July 2010 (4)
- June 2010 (9)
- May 2010 (3)
- April 2010 (2)
- March 2010 (6)
- February 2010 (7)